«Chusovoy Metallurgical Works», OJSC
- Construction and assembly works on cast-iron casing machine Nr 3.
- Construction and assembly works on modernization of ferroalloy manufacture.
- Construction and assembly works on the wastewater recycling area of vanadium manufacture.
- Construction and assembly works on the stove No. 5.
- Dismantling of hot-rolling mill 1840 and canteen No.2.
- Transfer of power grids due to elimination of hot-rolling mill 1840.
- Building works at gas-distributing unit. Gas metering station.
- Reconstruction of lixiviation and filtration unit. Ferroalloy melting.
- Reconstruction of mill 370 storage into chipping sector of cast house.
- Reconstruction of chemicals storage of Central plant laboratory.
- Reconstruction of KTP-2
- Annex to gas-smoky camera
- Construction and assembling works in the old-rolled workshop 250. Thermo strengthening line of reinforcing bars.
- Conversion of chemical departments for use of nitric acid instead of sulphuric acid.
- Erection of aluminothermic production of ferroalloys on the basis of technical pentoxide of vanadium.
- R&D, technical re-equipment of gas workshop, cutting ditch for sediment reservoir.
- Power circuits transfer.
- Arrangement of power supply at plant management building.
- Building and assembling works at compressor station.
- Designing for compressor station.
- Reconstruction of cable routing 6 kV PS GPP-1-TP.
- Construction works for express-laboratory.
- Building and assembly works, commissioning of Gas purification behind the converters of duplex-shop.
- Building works for stand of bucket drying and heating.
- Mounting of gas purification system for electric furnace, casting house.
- Wet gas purification of water recycling.
- Construction of purification system for process and aspiration gas of sintering shop, blast-furnace plant.
- Building and assembling works for “Dispatch of ferrovanadium to heavy haulers”.